Case: The project involved installing over 10,000 meters of fibre optic cable within a week for telecommunications infrastructure. The team at Ohmyfibre was responsible for ensuring the full network build, including reviewing and fixing any incomplete work left by previous teams.
The team at Ohmyfibre successfully installed over 10,000 meters of fibre in under a week, despite challenges such as incomplete work from previous teams and the need to review and fix existing networks. With five builds to complete, they faced significant pressure but embraced the challenge, showcasing their expertise and reliability.
The right tool for the job
A key factor in the project’s success was the use of the MicroFlow TOUCH from Fremco. Abder Abdallah, Telecoms Engineer at Ohmyfibre explains:
“Everything merged together from the machine combined with our hard work allowed us to complete this project. The simple use of the micro let me get 10k+ meters installed in just a few days, this has absolutely essential that the machine delivered because if the fibre wasn’t installed then the rest of the project would’ve been at a standstill.”
Abder Abdallah, Telecoms Engineer at Ohmyfibre
Ohmyfibre emphasizes the importance of proper setup in fibre installation projects, especially when managing multiple builds within tight deadlines. Abder compliments the machine for its compact size and powerful performance.
Abder Abdallah, Telecoms Engineer at Ohmyfibre
“It’s an absolutely brilliant piece of kit,” he said. “It doesn’t take up much space, which is crucial for us, allowing me to push fibre from the back of a van with comfort and ease. It’s super easy to set up and it only takes a few minutes to get it connected.””
The machine’s ease of setup and seamless operation played a vital role in the efficiency of the project. “…although it’s not as large as some other blowing machines it’s very powerful for its size and we can get some very large blows in, in just one go (800m+ with ease)” he added. “I’ve used other machines in the past and this has always been my favorite.”
Completing the project required not just the right tools but also precise planning and teamwork. Once all the maps were surveyed and missing cables were addressed, the fibre installation proceeded smoothly. The compact, sleek design of the machine, combined with the team’s hard work, allowed for seamless completion of the project. “One cannot be without the other,” the Abder concluded.
It will be interesting to follow future fiber blowing projects in the UK! Learn more about the MicroFlow Touch machine or MicroFlow LOG machine – making work easier for network owners, contractors and installers.
Read the post from Abder Abdallah
Looking for a fiber blowing machine in the UK? Go to our UK reseller Mills ltd. or see the list of our resellers around the world.
Have you read our latests news?
- Case story from UK: Ohmyfibre Tackles 5 Fibre Builds and Installs 10,000+ Meters within a Week
- Free 3-year extended warranty on all new Fremco Fiber Blowing machines
- Christmas Holiday Deadlines 2024
Follow us on LinkedIn or Facebook for more news and stories into fiber blowing